Line Marking Cost Guide 2025: What Actually Affects Your Pricing

19 November 2025 12 min readBy Niel Bennet
Facility manager reviewing line marking measurements in Dandenough South warehouse with contractor showing surface assessment

Last Tuesday, a facility manager from Campbellfield emailed us two almost identical warehouse floor plans. Same square meterage. Same forklift lanes. Same pedestrian walkways. He'd received quotes from three contractors and they were all over the place. One came in at roughly half the price of another. He wanted to know why.

Fair question. And the answer isn't as simple as "per square metre" pricing you might find on some websites (we learned the hard way those quotes rarely reflect reality).

Here's what we told him. Surface condition, material selection, compliance requirements, project timing, and access restrictions all dramatically change costs. A warehouse in Moorabbin with oil-contaminated concrete needs completely different prep than a new facility in Somerton with pristine flooring.

This guide breaks down every factor that affects line marking costs in Australia. No vague ranges. No made-up prices. Just the real variables that determine what you'll actually pay when we assess your site and provide a fixed quote.

[CTA 1] Upload your site plans and photos for an accurate, itemised quote within 48 hours. We'll explain exactly what affects your pricing and why.

Surface Type: Your Biggest Cost Variable

The ground you're marking determines everything. Not just the paint we use, but the prep work, application method, drying time, and ultimately how long those markings last.

Concrete Surfaces

New concrete is the easiest surface we work with. Clean, stable, consistent texture. But here's the thing most people don't realize: concrete needs to cure for at least 28 days before we can mark it. Rush that timeline and you'll see markings peel within months. The cement continues releasing moisture and that moisture destroys adhesion.

We assessed a warehouse in Dandenough South three years back. The developer wanted lines down two weeks after the slab pour. We said no. They found someone who said yes. Six months later we got called back to fix the entire floor after markings peeled off in sheets. That contractor's "cheap" quote ended up costing them nearly double to fix properly.

Old concrete presents different challenges. Surface contamination from oil, grease, hydraulic fluid, or years of accumulated dirt. Cracks that need filling. Sometimes the concrete's so porous it drinks paint like a sponge (which means we need more product).

A shopping centre in Laverton North had roughly 40% of their carpark contaminated with automotive fluids. We had to pressure clean at 3500 PSI, apply commercial degreaser, let it dry for 48 hours, then test moisture content before marking. That prep work took longer than the actual marking. But three years later, those lines are still perfect.

Asphalt Surfaces

Fresh asphalt needs six to eight weeks before marking. The bitumen contains oils that keep bleeding out during curing. Mark too early and those oils prevent adhesion.

Temperature affects asphalt differently than concrete. In summer, dark asphalt in western Sydney can hit 65°C on a clear afternoon. Standard waterborne paint on hot asphalt? Forget it. The paint dries before it bonds properly. That's when we use thermoplastic or schedule work for cooler hours.

We learned this the expensive way in 2017. A council carpark in Sunshine West, marked on a 38°C January day using standard waterborne. By March, roughly 30% of the markings were failing. We had to redo the project using thermoplastic at our cost. Around $8,000 lesson that taught us to either schedule appropriately or specify the right materials upfront.

Aged asphalt gets brittle and develops cracks. Those cracks need filling before marking or they'll telegraph through within months. Sometimes the surface is so degraded it needs rejuvenation treatment first.

Industrial Epoxy Floors

These are getting more common in warehouses, especially cold storage facilities and food processing plants. The epoxy coating provides a smooth, chemically resistant surface that's perfect for marking. But you need the right paint system.

Standard waterborne doesn't bond well to epoxy. You need two-pack epoxy line marking that chemically bonds to the floor coating. It costs more than waterborne but it's the only thing that works long-term.

A cold storage facility in Carrum Downs tried using standard paint on their epoxy floor. Forklift traffic had it wearing off within eight weeks. We came in with proper epoxy marking, did full surface preparation including light abrading for tooth, and applied our two-pack system. That was four years ago and the markings still look good.

Material Choices: Performance vs Budget

Every material has its place. Cheap isn't always wrong and expensive isn't always necessary. It depends entirely on your traffic, climate, and how long you need markings to last.

Waterborne Paint

This is our most economical option. Environmentally friendly, low VOC emissions, dries quickly, easy to apply. Perfect for light traffic areas or temporary markings. Indoor spaces with minimal vehicle traffic. Pedestrian walkways. Non-critical applications where repainting every 18 to 24 months isn't an issue.

The limitation? Durability. Heavy vehicle traffic, turning circles, and harsh weather will wear waterborne faster than other options. A warehouse in Braeside with 40+ forklift movements daily will chew through waterborne in under a year. That's when thermoplastic makes more financial sense despite the higher upfront cost.

We typically recommend waterborne for school playgrounds, sports courts without heavy use, internal warehouse pedestrian areas, and temporary traffic management. Places where the lower cost justifies more frequent repainting.

Thermoplastic

This is the workhorse of Australian line marking. Melted and applied at roughly 200°C, it cools into a durable, raised marking that lasts six to eight years in high-traffic applications.

Shopping centres. Busy carparks. Major roads. Anywhere vehicles are constantly turning, accelerating, or braking. Thermoplastic handles it all. The upfront cost is higher than waterborne but the lifecycle cost is usually lower because you're not repainting every year.

Glass beads get embedded during application for retroreflectivity (that's the technical term for how markings shine back at headlights at night). Essential for road marking. Required by AS 1742.3:2019 for line marking on roads and streets.

But here's what most contractors won't tell you: not all thermoplastic is equal. Grade A thermoplastic is specifically formulated for Australian heat. In western Sydney or northern Queensland, regular thermoplastic can soften on 40°C+ days. Grade A is rated to 50°C and won't pick up on vehicle tyres during summer.

We once specified standard thermoplastic for a carpark in Truganina. Second summer, we noticed slight softening during the January heatwave. Not enough to fail, but enough to make us switch to Grade A for all future projects in hot climates. Small details like that separate average work from professional results.

Epoxy and MMA (Methyl Methacrylate)

These are your premium options. Chemical-resistant, incredibly durable, perfect for industrial environments. Food processing. Chemical plants. Areas exposed to aggressive cleaning chemicals or specialized vehicles.

MMA is fast-curing and can be trafficked within an hour of application. Expensive but sometimes necessary when downtime is your biggest cost. A pharmaceutical warehouse in Tullamarine couldn't afford more than a four-hour shutdown window. MMA was the only option that met their timeline.

Epoxy takes longer to cure but provides exceptional durability and chemical resistance. It's what we use in cold storage facilities where moisture and extreme temperature fluctuations would destroy other materials.

Compliance Requirements Add Real Value (Not Just Cost)

Some clients see AS/NZS standards as annoying red tape. We see them as protection against liability, council fines, and workplace injuries. They exist because people got hurt when markings didn't meet specifications.

Carpark Compliance (AS/NZS 2890.1 and 2890.6)

AS/NZS 2890.1:2021 specifies minimum bay dimensions, aisle widths, sight lines, and traffic flow. Get it wrong and you risk council fines or insurance liability if an accident happens.

Standard parking bays need to be minimum 2.4m wide by 5.4m long. Seems simple until you're working with an existing carpark where someone eyeballed the layout years ago. We've measured bays as narrow as 2.1m in older facilities. That's non-compliant and opens you to liability.

Accessible parking under AS/NZS 2890.6:2009 is even more critical. Minimum 3.2m width for the bay itself, plus a 2.4m shared access aisle or 1.2m individual access zones. These aren't suggestions. They're legal requirements under the Disability Discrimination Act.

A strata manager in Coburg North got stung with a $4,800 fine because their accessible bays were marked at 2.9m. They hired the cheapest contractor who didn't verify dimensions. That "cheap" quote cost them the fine, plus properly remarking the bays, plus legal response time. Roughly $7,500 total when a compliant job would've been done right the first time.

We provide compliance documentation with every carpark project. Dimension verification, material certifications, and completion photos. If council comes knocking, you've got everything you need.

Warehouse Safety Compliance

Safe Work Australia regulations require clearly marked pedestrian walkways, forklift routes, loading zones, and emergency exits. This isn't optional. It's your legal obligation as an employer.

Yellow forklift lanes need to be minimum 150mm wide (most contractors do 100mm to save paint, which is non-compliant). Pedestrian walkways should be minimum 600mm wide and clearly distinguished from vehicle traffic zones.

We worked with a logistics company in Keysborough after they received a SafeWork notice. Their existing markings were faded, inconsistent widths, and didn't meet current standards. The inspector gave them 30 days to fix it or face potential facility shutdown. We had everything compliant within two weeks and provided full documentation for their response.

That's the value of compliance work. It's not just about avoiding fines. It's about protecting your workers and your business.

Road Marking Standards (AS 1742.3)

Council roads and public carparks need to meet Austroads specifications. Line widths, retroreflectivity, placement tolerances, all clearly defined. VicRoads and Transport for NSW both require approved contractors for road work.

We're VicRoads approved and work regularly with metropolitan councils across Melbourne. That approval means we know the standards, we have the right equipment, and we carry the required insurance coverage ($20M public liability, $10M professional indemnity).

Councils don't just want the work done. They want documentation. Traffic management plans. Material certifications. Completion reports with dimension verification. We provide all of that as standard because we've been doing this since 2009.

[CTA 2] Need compliance-ready line marking? Upload your plans now for a quote that includes all documentation, material certifications, and dimension verification.

When You Need It Done Affects Cost

Most line marking projects happen outside normal business hours. Carparks need to be empty. Roads need to be closed. Warehouses need to be clear of stock and forklifts. That timing affects labor costs, equipment requirements, and project complexity.

Weekend and Night Work

Shopping centres get marked Friday night through Sunday morning. Schools during term breaks. Warehouses overnight when operations shut down. That's just the reality of this work.

Night shifts aren't fun but that's when the work needs to happen. A crew working 8pm to 6am Saturday night costs more than the same crew working 7am to 3pm Wednesday. Penalty rates, lighting equipment, safety requirements all add to project costs.

We completed a shopping centre in Narre Warren over three consecutive Friday nights. 650 parking bays, 2,800 linear metres of marking, full traffic flow redesign. The centre needed to open at 9am Saturday with zero disruption to trading. That meant careful planning, efficient crew coordination, and backup plans if weather turned.

Could we have done it cheaper during weekday business hours? Absolutely. But the centre would've lost roughly $180,000 in trading revenue per day based on their figures. The night work premium was a tiny fraction of that cost.

Rush Projects

Sometimes you just need it done fast. Audit tomorrow. Council inspection next week. Grand opening in five days. We can usually accommodate urgent timelines but it comes at a cost.

That Campbellfield warehouse we mentioned earlier? The rushed Friday night assessment, Saturday quote, Sunday completion schedule required juggling other projects, calling in additional crew, and working a 12-hour shift instead of our standard eight-hour day. Could we do it? Yes. Did it cost more than a standard two-week timeline? Also yes.

We're always transparent about timing premiums. Most clients understand that mobilizing quickly requires flexibility from our end and that flexibility has a cost.

Weather Delays

Here's what every line marking contractor knows but doesn't always communicate clearly: weather can completely derail schedules. Paint needs dry conditions. Concrete needs to be moisture-free. Thermoplastic won't set properly in cold temperatures or wet conditions.

A logistics facility in Somerton was scheduled for remarking in early June 2023. We had three consecutive weather delays. Rain, rain, then more rain. The facility manager was frustrated (fair enough) but marking in wet conditions would've resulted in failure within weeks. Sometimes waiting is the only professional option.

Smart clients build buffer time into their schedules. If you absolutely need marking completed by a specific date, talk to us at least four to six weeks ahead. That gives us weather flexibility and ensures we're not rushing to meet an impossible deadline.

Project Scope: Size Matters (But Not How You Think)

Bigger isn't always proportionally more expensive. Equipment mobilization, site setup, and prep work all have fixed costs regardless of project size. A tiny 20-bay carpark can cost more per bay than a 200-bay carpark because we're spreading those fixed costs across fewer metres.

Small Projects

A single accessible parking bay. Ten metres of pedestrian crossing. Six forklift charging bays. These small projects often surprise clients with their costs. Why does 50 linear metres cost almost as much as 200 linear metres?

Because we still need to mobilize equipment, transport materials, set up safety barriers, prepare the surface, and clean up afterwards. Our crew still spends two hours travelling to Geelong regardless of whether we're marking 50 metres or 500 metres.

We're always honest about this. Sometimes combining multiple small maintenance items into one visit makes more financial sense than scheduling separate trips for each task. A facility in Scoresby schedules all their line marking maintenance twice yearly. Much more cost-effective than calling us out for individual fixes.

Large Projects

Major shopping centres. Industrial estates. Council road networks. These projects benefit from economies of scale. We can negotiate better material pricing. Setup costs get spread across thousands of metres. Crew efficiency improves when they're working the same site for multiple days.

A recent industrial estate in Derrimut involved 8,000 square metres of warehouse floor marking, external carpark marking, and road marking for the entire estate. That scale let us bring in specialized equipment, buy materials in bulk, and schedule efficiently across three weeks.

The client got better value per square metre than if they'd tackled each building separately over several months. Plus consistent quality across the entire estate because the same crew did everything.

Site Access: The Hidden Cost Factor

Can we drive equipment to the work area? Is there loading dock access? Three flights of stairs? These questions affect equipment choice, labor requirements, and ultimately costs.

Easy Access Sites

Ground-level carparks with direct vehicle access. Warehouses with loading dock access. These are our dream projects. We roll up with our line marking machine, set up, work efficiently, and pack up. No complications. No additional labor moving equipment by hand.

Restricted Access Sites

Basement carparks accessed by narrow ramps. Multi-level facilities requiring materials to be transported via service lifts. Rooftop carparks. Urban locations with limited parking for our vehicles.

We recently quoted a basement carpark in Melbourne CBD. Vehicle height restriction meant our standard line marking machine wouldn't fit. We had to use smaller hand-operated equipment which is slower and more labor-intensive. The client was surprised by the cost until we explained the access limitations.

Sometimes we need traffic management plans just to access the site. Roads with no parking. Busy loading areas. Security protocols at sensitive facilities. All of this adds time and cost but it's necessary to work safely and legally.

A pharmaceutical facility in Mulgrave required full security clearance for our crew, escorted access at all times, and vehicle inspections before entering the site. Those security requirements added roughly three hours to the project timeline. Necessary given the facility's needs, but definitely a cost factor.

What You're Actually Paying For (Beyond Just Paint)

When you upload plans and receive a quote from us, here's what's included in that fixed price. This isn't a mystery. It's the real breakdown of professional line marking.

Surface Assessment and Preparation

We don't just show up and start painting. Every project begins with surface assessment. Moisture testing for concrete (needs to be below 6% moisture content). Contamination check. Structural issues that need addressing. Measurement verification to ensure compliance.

Then comes preparation. Pressure cleaning to remove dirt, oil, and loose material. Crack filling where necessary. Surface grinding if adhesion requires it. Masking off areas that shouldn't be marked.

A warehouse in Preston had severe oil contamination near their loading docks. We spent nearly six hours on prep work for an area that took 90 minutes to mark. But that prep is why those markings are still perfect two years later while the rest of the floor (marked by a previous contractor who skipped prep) is failing.

Proper Materials and Application

We use specified materials for each application. Not whatever's cheapest. Not last year's leftover paint. The right material for your surface, traffic, and durability requirements.

Glass beads at the correct rate (typically 400g per square metre for road marking). Proper film thickness. Multiple coats where standards require them. These specifications exist for a reason and we follow them.

Traffic Management (When Required)

Road work and busy carparks need traffic management. Qualified traffic controllers (not just someone holding a stop sign). Proper signage. Safety barriers. Vehicle positioning that maintains traffic flow while keeping our crew safe.

This costs money. Controllers alone are $600+ per day each. But it's non-negotiable for safety and legal compliance. Safe Work Australia regulations are clear on this and we're not risking our crew's safety or your liability by cutting corners.

Compliance Documentation

Every project receives completion documentation. Photos showing before, during, and after conditions. Dimension verification for critical measurements. Material certifications showing product specifications and batch numbers. Application records noting temperatures, conditions, and cure times.

This documentation protects you. If council questions your accessible parking dimensions, you've got verification. If insurance questions your safety marking, you've got material certifications. If an audit challenges your compliance, you've got complete records.

We learned early on that documentation prevents disputes. A council in Ballarat questioned our line widths on a road project back in 2014. We provided dimension verification photos showing our tape measure against every critical measurement. Issue resolved immediately. Ever since, we document everything.

Warranty and Rectification Commitment

Professional contractors stand behind their work. If markings fail prematurely due to our application (not wear from traffic), we fix it at our cost. That warranty is factored into our pricing because we're confident in our work.

We've had to honor that warranty exactly three times in 16 years. Once when thermoplastic was applied in cold conditions and didn't bond properly. Once when a concrete slab had hidden moisture issues despite testing. Once when we simply got a measurement wrong (that expensive Moorabbin tennis court lesson we mentioned earlier).

Each time, we fixed it properly at our cost. That's what professional service means.

[CTA 3] Ready for accurate pricing on your project? Upload your site plans, photos, and specific requirements. We'll provide a detailed, itemised quote within 48 hours showing exactly what you're getting.

Why We Never Publish Price Lists

You've probably noticed we haven't listed any actual costs in this guide. That's deliberate. Here's why.

Every project is genuinely different. A "standard" carpark in Cheltenham might have perfect concrete, easy access, and flexible timing. Another "standard" carpark in Frankston might have contaminated asphalt, basement access restrictions, and night-work-only availability. Those projects have completely different costs despite similar square meterage.

Contractors who list prices either charge everyone the premium rate (so low-complexity clients overpay) or they lowball quotes then hit you with variations when reality doesn't match assumptions (you've probably experienced this frustration).

We learned back in 2011 that fixed quotes based on actual site assessment prevent disputes, surprises, and the awkward conversations about why the invoice doesn't match the estimate. As Niel often tells new clients: "I'd rather spend 90 minutes understanding your project properly and give you an accurate fixed price than guess on a phone call and surprise you later."

Getting Your Accurate Quote

Upload your site plans or sketches. Include photos if you've got them (especially showing surface condition). Tell us your timeline and any access restrictions. Note any compliance requirements or specific standards you need to meet.

We'll assess everything, ask clarifying questions if needed, and provide a detailed quote within 48 hours. That quote breaks down:

  • Surface preparation requirements
  • Material specifications and quantities
  • Labor and equipment costs
  • Traffic management if required
  • Compliance documentation included
  • Project timeline
  • Weather contingency approach
  • Fixed total price (not an estimate that changes)

If scope changes, we'll quote the variation before proceeding. No surprises at invoicing. That's how professional contracting should work.

5. CONTACT SECTION

Get Your Fixed-Price Quote

Line Marking Australia has been providing professional line marking services across Australia since 2009. We've completed 5,000+ projects for councils, facility managers, logistics companies, schools, and commercial property managers.

Director: Niel Bennet Phone: 0417 460 236 Email: info@linemarkingaustralia.com.au Address: 240 Plenty Road, Bundoora VIC 3083

Upload your plans now for a detailed quote within 48 hours.

We provide line marking services across all Australian states: Victoria, New South Wales, Queensland, Western Australia, South Australia, Tasmania, Australian Capital Territory, and Northern Territory.